- Any defects which happens within defects liability period ( DLP ) , Archi must write down on Schedule of Defects ( SoD) which must be given to Contractor within 14 days after DLP expires .
- Contractor must make good defects within 28 days after receiving SoD /
- If Contractor fails to do , Employer can appoint other Contractors . The cost set-off under Clause 30.4