Practical Completion and defect liability 2

  • When works are practically completed , Contractor must give written notice to Architect . Within 14 days , Architect should do either ;
  • If Archi thinks that works are not practically completed , Archi give notice ( with reasons ) to Contractor ( 1 copy to NSC ) .
  • If Archi thinks that work is practically completed , he can issue CPC .
  • Date of Practical Completion
- Date of receiving the make good works
- Date of written notice if there are no make good works .
  • CPC issued to Contractor , copies given to employer and NSC . Contractor shall return site ossession to employer .