Extension of Time

  • Submission of notice and particulars for EOT
- If Contractor feels that work will be delayed , hea can apply for EOT .
- Contractor give wirtten notice ( intention for EOT + estimated duration + causes for delay ) to Architect within 28days from the date of AI .
  • Delay by NSC

  • - If Contractor's delay includes NSC's delay , then he should forward a copy to NSC



  • Certificate of EOT
- Architect shall consider Contractor's submission and may reject it or issue Cert . of EOT within 6 weeks from the receipts of sufficient details .

  • Contractor to prevent delay
- Contractor must prevent and reduce delay in progress of work .

  • Notification to NSC
- Architect must notify all NSCs on later Completion Date.