- LAD and CNC
- - If Contractor fails to complete work on completion date ., Architect can issue Certificate of Non-Completion . Contractor shall pay ( based on the sum in appendix ) to Employer as LAD from Completion Date to Date of Practical Completion .
- Agreed LAD amount
- CNC revoked by subsequent Cert of EOT
- - if Architect issued Certificate of Extension of Time , this cert will revoke ( cancel ) off CNC .