A) any changes to the provisions in the Contract with regards
- Any limitation of working hours
-Working space
- Access to or utilisation of any specific part of the site .
- The execution and completion of thje work in any specific order .
But shall exclude any changes intended to rectify any negligence , omission , default and / or breach of contract by the Contractor and such changes shall be executed by the Contractor entirely at his own cost .
Each variation is considered separately and their net values carried forward to a general summary
The total values of omissions and the total value of additions are computed to arrive at a net balance which is added tp pr dedicted from the interim valuation .