- Delay in receipt of instructions , drawing details or levels from Architect . \
- Opening for inspection and testing where materials are found to be in accordance with contract .
- Delay in appointment of Artchitect or Quantity Surveyot
- Discrepancy or divergence in conditions , drawings specification or bills .
- Delays arising from nomination of Subcontractors .
- Delay in receiving possession or access
- Contractor suspending work in accordance with provisions of contract .
- Not all grounds entitilling Contractor to extension of time lead to automatic recovery of loss and expense .