  • Provide a continuous insecticide barrier between termite colony ( usually in the ground ) and the wood in building 
  • The pest control Association of Malaysia provides the Malaysian Anti - termite treatment guidelines . 
  • Pre-construction and Post - construction . 
  • Pre-construction - druing construction 
- horizontal barriers such as treating footing trench with insecticide before pouring concrete footings
-Apply diluted insecticide before pouring slab floors , slab supported porches , patio etc .
-Vertical barriers - establish chemical barriers in areas such as bases of foundation , plumbling , etc .


  • Post construction - in existing buildings . 
- Spraying organic preservatives directly to timbers with several coats .
( Drilled holes through concrete slab and apply diluted termiticide , seal up the holes ) .