- Loss and / or expenses caused by disturbance of regular progress of works
- THis means that what is recoverable is the financial loss and expenses which directly and naturally results in the ordinary course of occurrence of events .
Loss and expense
Therefore a contractor who claims direct loss / pr expenses must establish by use of oral or documentary evidence the followings :
- That he has suffered loss or incurred additional costs caused by occurrence of events specified in the provisions of Contract .
Demoinstrate that the loss or expenses or additional costs are sufficiently linked to the events set out in the contract .
- The loss or expenses or costs must be actual financial and not merelyu national loss . THe contractor must prove his case " on the balance of probabilities . "
-Must be able to prove the loss or expense or additional costs , reasonably to establish the probability that it has been incurred .