Thursday, October 6, 2011

Interim Valuation

  • General Procedure
  • Prior to issuing interim certificate , a QS must prepare interim valuation .
  • Main items to be considered
  1. Measured work , including preliminaries
  2. Value ofvariations and extras .
  3. Values of nominated sub-con and suppliers works
  4. Fluctuations
  5. Unfixed materials on site
  6. Retention monies
  7. Previous payments .
  8. Valuation - as accurate as possible
  9. Contractor is entitled to total values of work properly executed less a specified % of retention .
  10. Improperly retained sum could strain contractor - pay his debts .
  11. Employer must be protected against over payment , if insolvencies of contractor occurs , extra payments cannot be recovered . Liable to extra cost of selecting another contractor .
  12. Amount of measurement to be depends on nature and complexity of works and the stage they have reached .
  13. Common practice = contractor and QS meet regularly for the purpose of measuring works .

No comments:

Post a Comment