Obligations of the contractor

provide two copies of master work programme A.S.A.P after commencement date .

Contractor is not contractually bound to carry out work strictly in accordance with subnmitted work programme .

Contractor can amend the programme to take account of any extension of time (E.O.T) granted by Architect - submite revisions within 14 days of the awarded of E.O.T.

When the progress is likely to be delayed or is being delay , contractor must give written notice that comply .


  • Details of all the material circumstances surrounding the delay . 
  • State the cause of delay 
  • Identify which of the cause that the Contractor believes to be RELEVANT EVENTS . .