Contractor is not contractually bound to carry out work strictly in accordance with subnmitted work programme .
Contractor can amend the programme to take account of any extension of time (E.O.T) granted by Architect - submite revisions within 14 days of the awarded of E.O.T.
When the progress is likely to be delayed or is being delay , contractor must give written notice that comply .
- Details of all the material circumstances surrounding the delay .
- State the cause of delay
- Identify which of the cause that the Contractor believes to be RELEVANT EVENTS . .