- To give the architect the opportunity to take all reasonables steps available to minimise the effect of delays .
- To alert the Architect to watch out for the reasonableness of the contractor endeavours to prevent / minimise delays .
- To alert the Architect to the effects of the delays as they occur .
- To allow the Architect to advise the client .